The flooring contractor did the first landing and hallway this weekend. It is, however, not complete yet.

The contractors are coming back on Wednesday (4th December) and Thursday (5th December) to do the first set of stairs sanding & polishing so access will not be permitted for those two days. They will place a barrier or danger tape up the top of the stairs so that people can use the toilets

Once again, on Saturday and Sunday, 7th and 8th December, to do the last bit of flooring and then back again the following week to sand and polish the last set of stairs. They intend to start at 7am Saturday 7th December.

Spread the love - #manukaarcade